The vast majority of you readers have already found yourself in the situation of a party to a contract in which the rights and obligations of the parties were secured by a contractual penalty. If such a contract was concluded as part of the procurement procedure according to Act No. 134/2016 Coll., on public procurement, as amended (hereinafter referred to as "ZZVZ"), the text below regarding contractual fines in public contracts is just for you and can save you a lot of trouble!
In normal business dealings, the fulfillment of important obligations regulated by a written contract is usually confirmed by a contractual penalty. In the case of non-fulfillment of the contractual obligation properly and on time, an additional contractual sanction is imposed on the obliged contractual party, usually in the form of an obligation to pay monetary compensation to the other party, and possibly also the damage caused.
Whatever the wording of the contractual provision in question is conceived, this modification means option for the entitled party to calculate, apply and subsequently demand payment of the contractual penalty, or to legally recover it from the contractual partner.
However, the application of a contractual penalty is not usually a contractual obligation in private law relationships, but only options (as also follows from the wording of the law, i.e. in this case § 2048 para. 1 Act No. 89/2012 Coll., Civil Code). The penalty for breach of contractual obligation can thus be "capitalized" within the business relationship also through other ways in negotiations with the counterparty, such as additional multitasking at a good price, by shortening the implementation date etc.
Procurement
However, the situation is different for contracts concluded as part of a public contract according to the ZZVZ. The change of such an obligation is strictly regulated by law and is usually implemented in these situations by concluding a written amendment to the contract.
The conditions for changing the obligation are governed by § 222, paragraph 1 of the ZZVZ, which clearly states that the contracting authority may not allow a substantial change in the obligation from the contract to a public contract during its duration without carrying out a new procurement procedure.
Deviations from this provision are governed by the remaining paragraphs 2 – 10 of the mentioned provision of the ZZVZ.
However, according to the established decision-making practice of the Czech courts, the possible non-application of the contractual penalty to which the public procurement contract is entitled is such a substantial change to the contract that the contracting authority is prohibited by the ZZVZ.
It is considered that the terms of the contract are clearly defined for the purposes of the tendering procedure, the text of the contract is attached to the public contract and contains conditions with which the participants of the public contract have the opportunity to become familiar during the tendering procedure and these conditions can and should be included in their possible offer take into account.
Contract fine in public contracts
Courts repeatedly state that any non-enforcement of the contractual penalty, to which the client was entitled due to breach of contractual obligations by the supplier, means as a consequence a material change in the commitment, and that, in layman's terms, for the reason that if the other participants in the public contract knew in advance that the specified contractual penalty would not be enforced, i.e. as if it were not in the contract, it would affect their own bids in the procurement procedure.
Section 222 of the ZZVZ is therefore intended to effectively prevent the legal and factual conditions of the performance of a public contract from differing substantially from the contract conditions.
When assessing whether there has been a change in the commitment, it is therefore necessary to compare the situation that resulted from the tender conditions, and which potential suppliers could reasonably expect based on these conditions, with the actual progress of the contract. It is quite easy to imagine situations in which the contractual obligation covered by the contractual penalty is so important that it can substantially lower the offer price affect, such as the date of completion of the order, compliance with the quality standards of the supplied goods or services, fulfillment of qualification and other prerequisites, etc.
If, subsequently, the contracting authority does not apply the contractual penalty during the implementation of the contract, it acts significantly differently than it was clear from the contract conditions.
Therefore, the contractor must apply the contractual penalty not only to himself suppliers, but in case of non-payment in a proper and timely manner, also with the relevant one court, no later than the statute of limitations.
Even if he ultimately decides to apply it, but does so with a long time gap, even before the claims expire, this means that the contractor must pay the contractual penalty much later than was stipulated in the terms of reference.
With regard to the time value of money (primarily the cost of lost opportunities and inflation), even such a significantly delayed application of the contractual penalty represents an advantage in itself. Likewise, if the contracting authority were to call on the supplier without undue delay to pay the contractual penalty and the latter would not pay it, he would also have to pay interest on late payment. It is precisely with regard to the time value of money (either in the form of a longer time to obtain the necessary funds or in the form of the interest-free possibility to continue to deal with them freely) that the postponement of the obligation to pay the contractual penalty in itself is essential favoring the supplier.
The contracting authority should also apply the contractual penalty in its full amount, since even its possible moderation (reduction) by the contracting authority could be considered a substantial and generally inadmissible change to the contract according to § 222 ZZVZ.
Even if it is only a partial waiver of the contractual penalty, according to the regulation contained in § 1995, paragraph 1 of the Civil Code, it is associated with the fiction of the supplier's consent, if the latter has not expressed his disapproval without undue delay, expressly or tacitly, by paying such a contractual penalty. From the point of view of civil law, debt forgiveness is therefore conceptually an agreement on the (partial) extinction of an obligation and therefore from our point of view a change of contract.
Claims for the application of a contractual penalty in public contracts
On the contrary, however, it must also be emphasized that any immediate non-application of the right of the contracting authority does not always necessarily mean a substantial change in the obligation in the sense of § 222 paragraph 1 ZZVZ.
As the Supreme Administrative Court of the Czech Republic states in the justification of one of its decisions, it is necessary in each individual case evaluate all factual circumstances of the given case.
In other situations, it may be justified not to assert certain claims at a given time. The reason for the reasonable delay may be, for example, that the contracting authority claims yet evaluates, that the claims are uncertain or questionable, that the contracting authority is gathering evidence for them, that the contracting authority is conducting negotiations with the supplier on the payment or other settlement of these claims, and the like.
záver
With regard to the above, it is therefore necessary from the position of the public procurement contractor to consistently weigh which obligations will be confirmed by a contractual penalty, and in the event of non-compliance with such an obligation by the supplier, there should be exceptions provided by law or jurisprudence for full and immediate application such contractual penalties against the supplier.
Source: leagleone
Do you have questions about the application of contractual clauses in the procurement procedure? You need other legal advice regarding public contracts? Don't know how to prepare a tender? We will advise you!

Mgr. Vladimír Nováček, attorney